An efficient genetic algorithm for decentralized multi-project scheduling with resource transfers
School of Management, Northwestern Polytechnical University, Xi’an 710072, Shaanxi, China |
This paper investigates the decentralized resource-constrained multi-project scheduling problem with transfer times (DRCMPSPTT) in which the transfer times of the global resources among different projects are assumed to be sequence-independent, while transfers of local resources take no time within a project. First, two decision variables ($ {y_{ijg}} $ and $ {w_{ijg}} $) are adopted to express the transition state of global resources between projects. $ {y_{ijg}} $ (takes a value of 0 or 1) represents whether activity i transfers global resource g to activity j; accordingly, the transferred quantity is denoted as $ {w_{ijg}} $. Then, we construct an integer linear model with the goal of minimizing the average project delay for the DRCMPSPTT. Second, an adaptive genetic algorithm (GA) is developed to solve the DRCMPSPTT. To gain the schedules for the DRCMPSPTT, the traditional serial and parallel scheduling generation schemes (SGSs) are modified to combine with different resource transfer rules and to design multiple decoding schemes. Third, the numerical experiments are implemented to analyse the effects of eight decoding schemes, and we found that the scheme comprising the parallel SGS and maxRS rule can make the GA work the best; furthermore, the effectiveness of the GA_maxRS (GA embedded with the best scheme) is demonstrated by solving some instances with different sizes.
References:
[1] |
S. Adhau, M. L. Mittal and A. Mittal,
A multi-agent system for decentralized multi project scheduling with resource transfers, International Journal of Production Economics, 146 (2013), 646-661.
doi: 10.1016/j.ijpe.2013.08.013. |
[2] |
S. Adhau, M. L. Mittal and A. Mittal,
A multi-agent system for distributed multi-project scheduling: An auction-based negotiation approach, Engineering Applications of Artificial Intelligence, 25 (2012), 1738-1751.
doi: 10.1016/j.engappai.2011.12.003. |
[3] |
B. Afshar-Nadjafi and M. Majlesi,
Resource constrained project scheduling problem with setup times after preemptive processes, Computers and Chemical Engineering, 69 (2014), 16-25.
doi: 10.1016/j.compchemeng.2014.06.012. |
[4] |
C. Artigues, P. Michelon and S. Reusser,
Insertion techniques for static and dynamic resource-constrained project scheduling, European Journal of Operational Research, 149 (2003), 249-267.
doi: 10.1016/S0377-2217(02)00758-0. |
[5] |
D. Bedworth and J. Bailey, Integrated Production Control Systems Management, Analysis, Design, 2$^nd$ edition, John Wiley & Sons, Inc., New York, 1999. Google Scholar |
[6] |
C. Bierwirth, D. Mattfeld and H. Kopfer, On permutation representations for scheduling problems, in Parallel Problem Solving from Nature, Lecture Notes in Computer Science, 1996,310–318.
doi: 10.1007/3-540-61723-X_995. |
[7] |
P. Brucker, S. Knust, A. Schoo and O. Thiele,
A branch and bound algorithm for the resource-constrained project scheduling problem, European Journal of Operational Research, 107 (1998), 272-288.
doi: 10.1016/S0377-2217(97)00335-4. |
[8] |
Z. Cai and X. Li, A hybrid genetic algorithm for resource-constrained multi-project scheduling problem with resource transfer time, IEEE International Conference on Automation Science and Engineering, Seoul, 2012,569–574.
doi: 10.1109/CoASE.2012.6386457. |
[9] |
G. Confessore, S. Giordani and S. Rismondo,
A market-based multi-agent system model for decentralized multi–project scheduling, Annals of Operations Research, 150 (2007), 115-135.
doi: 10.1007/s10479-006-0158-9. |
[10] |
E. W. Davis,
Project network summary measures constrained resource scheduling, AIIE Transactions, 7 (1975), 132-142.
doi: 10.1080/05695557508974995. |
[11] |
E. L. Demeulemeester and W. S. Herroelen,
An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problem, European Journal of Operational Research, 90 (1996), 334-348.
doi: 10.1016/0377-2217(95)00358-4. |
[12] |
L. Djerid, M. C. Portman and P. Villon,
Performance analysis of permutation cross-over genetic operators, Journal of Decision Systems, 5 (1996), 131-140.
doi: 10.1080/12460125.1996.10511679. |
[13] |
S. Hartmann and R. Kolisch,
Experimental evaluation of state-of-the-art heuristics for resource-constrained project scheduling problem, European Journal of Operational Research, 127 (2000), 394-407.
doi: 10.1016/S0377-2217(99)00485-3. |
[14] |
J. B. Holland and J. H. Holland, Adaption in Natural and Artificial Systems, University of Michigan Press, Ann Arbor, Mich., 1975.
![]() |
[15] |
J. Homberger,
A multi-agent system for the decentralized resource constrained multi-project scheduling problem, International Transactions in Operational Research, 14 (2007), 565-589.
doi: 10.1111/j.1475-3995.2007.00614.x. |
[16] |
J. Homberger,
A (${\mu}$, ${\lambda}$)-coordination mechanism for agent-based multi-project scheduling, OR Spectrum, 34 (2012), 107-132.
doi: 10.1007/s00291-009-0178-3. |
[17] |
R. Jans and Z. Degraeve,
Modeling industrial lot sizing problems: A review, International Journal of Production Research, 46 (2008), 1619-1643.
doi: 10.1080/00207540600902262. |
[18] |
R. L. Kadri and F. F. Boctor, An efficient genetic algorithm to solve the resource-constrained project scheduling problem with transfer times: The single mode case, European Journal of Operational Research, 265 (2018), 454-–462.
doi: 10.1016/j.ejor.2017.07.027. |
[19] |
J. E. Kelley, The critical-path method: Resources planning and scheduling, Industrial Scheduling, 13 (1963), 347365. Google Scholar |
[20] |
S. Khalilpourazari, B. Naderi and S. Khalilpourazary, Multi-objective stochastic fractal search: A powerful algorithm for solving complex multi-objective optimization problems, Soft Computing, 24 (2020), 3037–-3066.
doi: 10.1007/s00500-019-04080-6. |
[21] |
S. Khalilpourazari and S. H. R. Pasandideh,
Modeling and optimization of multi-item multi-constrained EOQ model for growing items, Knowledge-Based Systems, 164 (2019), 150-162.
doi: 10.1016/j.knosys.2018.10.032. |
[22] |
S. Khalilpourazari and S. H. R. Pasandideh, Sine-cosine crow search algorithm: Theory and applications, Neural Computing and Applications, 32 (2019), 7725–-7742.
doi: 10.1007/s00521-019-04530-0. |
[23] |
R. Kolisch, Project scheduling with setup times, in Project Scheduling Under Resource Constraints, Production and Logistics, Physica, Heidelberg, 1995,177–185.
doi: 10.1007/978-3-642-50296-5_8. |
[24] |
R. Kolisch and S. Hartmann, Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification and computational analysis, in Project Scheduling, International Series in Operations Research & Management Science, Springer, Boston, 1999,147–178.
doi: 10.1007/978-1-4615-5533-9_7. |
[25] |
R. Kolisch and A. Sprecher, PSPLIB–A project scheduling library, European Journal of Operation Research, 96 (1996), 205-216. Google Scholar |
[26] |
D. Kruger and A. Scholl,
A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times, European Journal of Operation Research, 197 (2009), 492-508.
doi: 10.1016/j.ejor.2008.07.036. |
[27] |
D. Kruger and A. Scholl,
Managing and modelling general resource transfers in (multi-)project scheduling, OR Spectrum, 32 (2010), 369-394.
doi: 10.1007/s00291-008-0144-5. |
[28] |
C. J. Liao, C. W. Chao and L. C. Chen,
An improved heuristic for parallel machine weighted flowtime scheduling with family set-up times, Computers and Mathematics with Applications, 63 (2012), 110-117.
doi: 10.1016/j.camwa.2011.10.077. |
[29] |
A. Lova and P. Tormos,
Analysis of scheduling schemes and heuristic rules performance in resource-constrained multiproject scheduling, Annals of Operations Research, 102 (2001), 263-286.
doi: 10.1023/A:1010966401888. |
[30] |
A. Lova, P. Tormos, M. Cervantes and F. Barber,
An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes, International Journal of Production Economics, 117 (2009), 302-316.
doi: 10.1016/j.ijpe.2008.11.002. |
[31] |
D. Merkle, M. Middendorf and H. Schmeck,
Ant colony optimization for resource-constrained project scheduling, IEEE Transactions on Evolutionary Computation, 6 (2002), 333-346.
doi: 10.1109/TEVC.2002.802450. |
[32] |
M. Mika, G. Waligra and J. Weglarz,
Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times, European Journal of Operational Research, 187 (2008), 1238-1250.
doi: 10.1016/j.ejor.2006.06.069. |
[33] |
M. L. Mittal and A. Kanda,
Scheduling of multiple projects with resource transfers, International Journal of Mathematics in Operational Research, 1 (2009), 303-325.
doi: 10.1504/IJMOR.2009.024288. |
[34] |
K. Moumene and J. A. Ferland,
Activity list representation for a generalization of the resource-constrained project scheduling problem, European Journal of Operational Research, 199 (2009), 46-54.
doi: 10.1016/j.ejor.2008.10.030. |
[35] |
M. S. Nagano, A. A. Silva and L. A. N. Lorena,
A new evolutionary clustering search for a no-wait flow shop problem with set-up times, Engineering Applications of Artificial Intelligence, 25 (2012), 1114-1120.
doi: 10.1016/j.engappai.2012.05.017. |
[36] |
K. Neumann, C. Schwindt and J. Zimmermann, Project Scheduling with Time Windows and Scarce Resources, Springer-Verlag, Berlin, 2002.
doi: 10.1007/978-3-540-24800-2. |
[37] |
S. H. R. Pasandideh and S. Khalilpourazari, Sine cosine crow search algorithm: A powerful hybrid meta heuristic for global optimization, preprint, arXiv: 1801.08485. Google Scholar |
[38] |
J. Poppenborg and S. Knust,
A flow-based tabu search algorithm for the RCPSP with transfer times, OR Spectrum, 38 (2016), 305-334.
doi: 10.1007/s00291-015-0402-2. |
[39] |
V. Roshanaei, B. Naderi, F. Jolai and M. Khalili,
A variable neighborhood search for job shop scheduling with set-up times to minimize makespan, Future Generation Computer Systems, 25 (2009), 654-661.
doi: 10.1016/j.future.2009.01.004. |
[40] |
M. Rostami, M. Bagherpour, M. M. Mazdeh and A. Makui, Resource Pool Location for Periodic Services in Decentralized Multi-Project Scheduling Problems, Journal of Computing in Civil Engineering, 31 (2017), 04017022.
doi: 10.1061/(ASCE)CP.1943-5487.0000671. |
[41] |
V. Valls, F. Ballestin and M. S. Quintanilla, A hybrid genetic algorithm for the RCPSP, Technical report, Department of Statistics and Operations Research, University of Valencia, 2003. Google Scholar |
[42] |
V. Valls, F. Ballestin and M. S. Quintanilla,
Justification and RCPSP: A technique that pays, European Journal of Operational Research, 165 (2005), 375-386.
doi: 10.1016/j.ejor.2004.04.008. |
[43] |
M. Vanhoucke,
Setup times and fast tracking in resource-constrained project scheduling, Computers & Industrial Engineering, 54 (2008), 1062-1070.
doi: 10.1016/j.cie.2007.11.008. |
[44] |
K. K. Yang and C. C. Sum,
A comparison of resource allocation and activity scheduling rules in a dynamic multi-project environment, Journal of Operation Management, 11 (1993), 207-218.
doi: 10.1016/0272-6963(93)90023-I. |
[45] |
K. K. Yang and C. C. Sum, An evaluation of due date, resource allocation, project release, and activity scheduling rules in a multi project environment, European Journal of Operational Research, 103 (1997), 139-154. Google Scholar |
show all references
References:
[1] |
S. Adhau, M. L. Mittal and A. Mittal,
A multi-agent system for decentralized multi project scheduling with resource transfers, International Journal of Production Economics, 146 (2013), 646-661.
doi: 10.1016/j.ijpe.2013.08.013. |
[2] |
S. Adhau, M. L. Mittal and A. Mittal,
A multi-agent system for distributed multi-project scheduling: An auction-based negotiation approach, Engineering Applications of Artificial Intelligence, 25 (2012), 1738-1751.
doi: 10.1016/j.engappai.2011.12.003. |
[3] |
B. Afshar-Nadjafi and M. Majlesi,
Resource constrained project scheduling problem with setup times after preemptive processes, Computers and Chemical Engineering, 69 (2014), 16-25.
doi: 10.1016/j.compchemeng.2014.06.012. |
[4] |
C. Artigues, P. Michelon and S. Reusser,
Insertion techniques for static and dynamic resource-constrained project scheduling, European Journal of Operational Research, 149 (2003), 249-267.
doi: 10.1016/S0377-2217(02)00758-0. |
[5] |
D. Bedworth and J. Bailey, Integrated Production Control Systems Management, Analysis, Design, 2$^nd$ edition, John Wiley & Sons, Inc., New York, 1999. Google Scholar |
[6] |
C. Bierwirth, D. Mattfeld and H. Kopfer, On permutation representations for scheduling problems, in Parallel Problem Solving from Nature, Lecture Notes in Computer Science, 1996,310–318.
doi: 10.1007/3-540-61723-X_995. |
[7] |
P. Brucker, S. Knust, A. Schoo and O. Thiele,
A branch and bound algorithm for the resource-constrained project scheduling problem, European Journal of Operational Research, 107 (1998), 272-288.
doi: 10.1016/S0377-2217(97)00335-4. |
[8] |
Z. Cai and X. Li, A hybrid genetic algorithm for resource-constrained multi-project scheduling problem with resource transfer time, IEEE International Conference on Automation Science and Engineering, Seoul, 2012,569–574.
doi: 10.1109/CoASE.2012.6386457. |
[9] |
G. Confessore, S. Giordani and S. Rismondo,
A market-based multi-agent system model for decentralized multi–project scheduling, Annals of Operations Research, 150 (2007), 115-135.
doi: 10.1007/s10479-006-0158-9. |
[10] |
E. W. Davis,
Project network summary measures constrained resource scheduling, AIIE Transactions, 7 (1975), 132-142.
doi: 10.1080/05695557508974995. |
[11] |
E. L. Demeulemeester and W. S. Herroelen,
An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problem, European Journal of Operational Research, 90 (1996), 334-348.
doi: 10.1016/0377-2217(95)00358-4. |
[12] |
L. Djerid, M. C. Portman and P. Villon,
Performance analysis of permutation cross-over genetic operators, Journal of Decision Systems, 5 (1996), 131-140.
doi: 10.1080/12460125.1996.10511679. |
[13] |
S. Hartmann and R. Kolisch,
Experimental evaluation of state-of-the-art heuristics for resource-constrained project scheduling problem, European Journal of Operational Research, 127 (2000), 394-407.
doi: 10.1016/S0377-2217(99)00485-3. |
[14] |
J. B. Holland and J. H. Holland, Adaption in Natural and Artificial Systems, University of Michigan Press, Ann Arbor, Mich., 1975.
![]() |
[15] |
J. Homberger,
A multi-agent system for the decentralized resource constrained multi-project scheduling problem, International Transactions in Operational Research, 14 (2007), 565-589.
doi: 10.1111/j.1475-3995.2007.00614.x. |
[16] |
J. Homberger,
A (${\mu}$, ${\lambda}$)-coordination mechanism for agent-based multi-project scheduling, OR Spectrum, 34 (2012), 107-132.
doi: 10.1007/s00291-009-0178-3. |
[17] |
R. Jans and Z. Degraeve,
Modeling industrial lot sizing problems: A review, International Journal of Production Research, 46 (2008), 1619-1643.
doi: 10.1080/00207540600902262. |
[18] |
R. L. Kadri and F. F. Boctor, An efficient genetic algorithm to solve the resource-constrained project scheduling problem with transfer times: The single mode case, European Journal of Operational Research, 265 (2018), 454-–462.
doi: 10.1016/j.ejor.2017.07.027. |
[19] |
J. E. Kelley, The critical-path method: Resources planning and scheduling, Industrial Scheduling, 13 (1963), 347365. Google Scholar |
[20] |
S. Khalilpourazari, B. Naderi and S. Khalilpourazary, Multi-objective stochastic fractal search: A powerful algorithm for solving complex multi-objective optimization problems, Soft Computing, 24 (2020), 3037–-3066.
doi: 10.1007/s00500-019-04080-6. |
[21] |
S. Khalilpourazari and S. H. R. Pasandideh,
Modeling and optimization of multi-item multi-constrained EOQ model for growing items, Knowledge-Based Systems, 164 (2019), 150-162.
doi: 10.1016/j.knosys.2018.10.032. |
[22] |
S. Khalilpourazari and S. H. R. Pasandideh, Sine-cosine crow search algorithm: Theory and applications, Neural Computing and Applications, 32 (2019), 7725–-7742.
doi: 10.1007/s00521-019-04530-0. |
[23] |
R. Kolisch, Project scheduling with setup times, in Project Scheduling Under Resource Constraints, Production and Logistics, Physica, Heidelberg, 1995,177–185.
doi: 10.1007/978-3-642-50296-5_8. |
[24] |
R. Kolisch and S. Hartmann, Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification and computational analysis, in Project Scheduling, International Series in Operations Research & Management Science, Springer, Boston, 1999,147–178.
doi: 10.1007/978-1-4615-5533-9_7. |
[25] |
R. Kolisch and A. Sprecher, PSPLIB–A project scheduling library, European Journal of Operation Research, 96 (1996), 205-216. Google Scholar |
[26] |
D. Kruger and A. Scholl,
A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times, European Journal of Operation Research, 197 (2009), 492-508.
doi: 10.1016/j.ejor.2008.07.036. |
[27] |
D. Kruger and A. Scholl,
Managing and modelling general resource transfers in (multi-)project scheduling, OR Spectrum, 32 (2010), 369-394.
doi: 10.1007/s00291-008-0144-5. |
[28] |
C. J. Liao, C. W. Chao and L. C. Chen,
An improved heuristic for parallel machine weighted flowtime scheduling with family set-up times, Computers and Mathematics with Applications, 63 (2012), 110-117.
doi: 10.1016/j.camwa.2011.10.077. |
[29] |
A. Lova and P. Tormos,
Analysis of scheduling schemes and heuristic rules performance in resource-constrained multiproject scheduling, Annals of Operations Research, 102 (2001), 263-286.
doi: 10.1023/A:1010966401888. |
[30] |
A. Lova, P. Tormos, M. Cervantes and F. Barber,
An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes, International Journal of Production Economics, 117 (2009), 302-316.
doi: 10.1016/j.ijpe.2008.11.002. |
[31] |
D. Merkle, M. Middendorf and H. Schmeck,
Ant colony optimization for resource-constrained project scheduling, IEEE Transactions on Evolutionary Computation, 6 (2002), 333-346.
doi: 10.1109/TEVC.2002.802450. |
[32] |
M. Mika, G. Waligra and J. Weglarz,
Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times, European Journal of Operational Research, 187 (2008), 1238-1250.
doi: 10.1016/j.ejor.2006.06.069. |
[33] |
M. L. Mittal and A. Kanda,
Scheduling of multiple projects with resource transfers, International Journal of Mathematics in Operational Research, 1 (2009), 303-325.
doi: 10.1504/IJMOR.2009.024288. |
[34] |
K. Moumene and J. A. Ferland,
Activity list representation for a generalization of the resource-constrained project scheduling problem, European Journal of Operational Research, 199 (2009), 46-54.
doi: 10.1016/j.ejor.2008.10.030. |
[35] |
M. S. Nagano, A. A. Silva and L. A. N. Lorena,
A new evolutionary clustering search for a no-wait flow shop problem with set-up times, Engineering Applications of Artificial Intelligence, 25 (2012), 1114-1120.
doi: 10.1016/j.engappai.2012.05.017. |
[36] |
K. Neumann, C. Schwindt and J. Zimmermann, Project Scheduling with Time Windows and Scarce Resources, Springer-Verlag, Berlin, 2002.
doi: 10.1007/978-3-540-24800-2. |
[37] |
S. H. R. Pasandideh and S. Khalilpourazari, Sine cosine crow search algorithm: A powerful hybrid meta heuristic for global optimization, preprint, arXiv: 1801.08485. Google Scholar |
[38] |
J. Poppenborg and S. Knust,
A flow-based tabu search algorithm for the RCPSP with transfer times, OR Spectrum, 38 (2016), 305-334.
doi: 10.1007/s00291-015-0402-2. |
[39] |
V. Roshanaei, B. Naderi, F. Jolai and M. Khalili,
A variable neighborhood search for job shop scheduling with set-up times to minimize makespan, Future Generation Computer Systems, 25 (2009), 654-661.
doi: 10.1016/j.future.2009.01.004. |
[40] |
M. Rostami, M. Bagherpour, M. M. Mazdeh and A. Makui, Resource Pool Location for Periodic Services in Decentralized Multi-Project Scheduling Problems, Journal of Computing in Civil Engineering, 31 (2017), 04017022.
doi: 10.1061/(ASCE)CP.1943-5487.0000671. |
[41] |
V. Valls, F. Ballestin and M. S. Quintanilla, A hybrid genetic algorithm for the RCPSP, Technical report, Department of Statistics and Operations Research, University of Valencia, 2003. Google Scholar |
[42] |
V. Valls, F. Ballestin and M. S. Quintanilla,
Justification and RCPSP: A technique that pays, European Journal of Operational Research, 165 (2005), 375-386.
doi: 10.1016/j.ejor.2004.04.008. |
[43] |
M. Vanhoucke,
Setup times and fast tracking in resource-constrained project scheduling, Computers & Industrial Engineering, 54 (2008), 1062-1070.
doi: 10.1016/j.cie.2007.11.008. |
[44] |
K. K. Yang and C. C. Sum,
A comparison of resource allocation and activity scheduling rules in a dynamic multi-project environment, Journal of Operation Management, 11 (1993), 207-218.
doi: 10.1016/0272-6963(93)90023-I. |
[45] |
K. K. Yang and C. C. Sum, An evaluation of due date, resource allocation, project release, and activity scheduling rules in a multi project environment, European Journal of Operational Research, 103 (1997), 139-154. Google Scholar |











Authors | Project | Objective | Transfer times | Algorithm | ||||
Single | Multi- | Decentralized multi- | Makespan | Others | sequence-dependent | sequence-independent | ||
Kolisch (1995) | Parallel scheme based heuristic | |||||||
Neumann et al (2003) | Branch-and-bound | |||||||
Vanhoucke(2008) | Branch-and-bound | |||||||
Mika (2008) | Tabu search | |||||||
Afshar-Nadjafi et al (2014) | GA | |||||||
Poppenborg(2016) | Tabu search | |||||||
Kadri and Boctor (2017) | GA | |||||||
Yang and Sum(1993, 1997) | Computational experiment | |||||||
Mittal and Kanda (2009) | Cost | Heuristics | ||||||
Kruger and Scholl(2009, 2010) | Cost | Priority-rule based heuristic | ||||||
Cai and Li(2012) | APD | Hybrid GA | ||||||
Adhau and Mittal(2013) | APD | DMAS/RIA | ||||||
This research | APD | GA |
Authors | Project | Objective | Transfer times | Algorithm | ||||
Single | Multi- | Decentralized multi- | Makespan | Others | sequence-dependent | sequence-independent | ||
Kolisch (1995) | Parallel scheme based heuristic | |||||||
Neumann et al (2003) | Branch-and-bound | |||||||
Vanhoucke(2008) | Branch-and-bound | |||||||
Mika (2008) | Tabu search | |||||||
Afshar-Nadjafi et al (2014) | GA | |||||||
Poppenborg(2016) | Tabu search | |||||||
Kadri and Boctor (2017) | GA | |||||||
Yang and Sum(1993, 1997) | Computational experiment | |||||||
Mittal and Kanda (2009) | Cost | Heuristics | ||||||
Kruger and Scholl(2009, 2010) | Cost | Priority-rule based heuristic | ||||||
Cai and Li(2012) | APD | Hybrid GA | ||||||
Adhau and Mittal(2013) | APD | DMAS/RIA | ||||||
This research | APD | GA |
Transfer rules | Priority value |
Extremum |
minTT | min | |
minGAP | min | |
maxRS | max | |
minRS | min |
Transfer rules | Priority value |
Extremum |
minTT | min | |
minGAP | min | |
maxRS | max | |
minRS | min |
Problem subset | NOI | Characterization per instance | UF |
||
MP30_2 | 5 | 2 | 30 | (1;3)/(2;2)/(3;1) | 0.84 |
MP90_2 | 5 | 2 | 90 | (1;3)/(2;2)/(3;1) | 0.57 |
MP120_2 | 5 | 2 | 120 | (1;3)/(2;2)/(3;1) | 1.31 |
MP30_5 | 5 | 5 | 30 | (1;3)/(2;2)/(3;1) | 0.82 |
MP90_5 | 5 | 5 | 90 | (1;3)/(2;2)/(3;1) | 0.61 |
MP120_5 | 5 | 5 | 120 | (1;3)/(2;2)/(3;1) | 1.32 |
MP30_10 | 5 | 10 | 30 | (1;3)/(2;2)/(3;1) | 2.38 |
MP90_10 | 5 | 10 | 90 | (1;3)/(2;2)/(3;1) | 1.14 |
MP120_10 | 5 | 10 | 120 | (1;3)/(2;2)/(3;1) | 1.91 |
MP30_20 | 5 | 20 | 30 | (1;3)/(2;2)/(3;1) | 3.37 |
MP90_20 | 5 | 20 | 90 | (1;3)/(2;2)/(3;1) | 0.9 |
MP120_20 | 5 | 20 | 120 | (1;3)/(2;2)/(3;1) | 0.87 |
Problem subset | NOI | Characterization per instance | UF |
||
MP30_2 | 5 | 2 | 30 | (1;3)/(2;2)/(3;1) | 0.84 |
MP90_2 | 5 | 2 | 90 | (1;3)/(2;2)/(3;1) | 0.57 |
MP120_2 | 5 | 2 | 120 | (1;3)/(2;2)/(3;1) | 1.31 |
MP30_5 | 5 | 5 | 30 | (1;3)/(2;2)/(3;1) | 0.82 |
MP90_5 | 5 | 5 | 90 | (1;3)/(2;2)/(3;1) | 0.61 |
MP120_5 | 5 | 5 | 120 | (1;3)/(2;2)/(3;1) | 1.32 |
MP30_10 | 5 | 10 | 30 | (1;3)/(2;2)/(3;1) | 2.38 |
MP90_10 | 5 | 10 | 90 | (1;3)/(2;2)/(3;1) | 1.14 |
MP120_10 | 5 | 10 | 120 | (1;3)/(2;2)/(3;1) | 1.91 |
MP30_20 | 5 | 20 | 30 | (1;3)/(2;2)/(3;1) | 3.37 |
MP90_20 | 5 | 20 | 90 | (1;3)/(2;2)/(3;1) | 0.9 |
MP120_20 | 5 | 20 | 120 | (1;3)/(2;2)/(3;1) | 0.87 |
Problem subsets | Serial | parallel | |||||||
minTT | minGAP | maxRS | minRS | minTT | minGAP | maxRS | minRS | ||
MP30_2 | 14.8 | 13.7 | 14.8 | 16.1 | 13.9 | 13.3 | 13.7 | 14 | |
MP90_2 | 10 | 8.8 | 10.1 | 11.3 | 6.9 | 6.8 | 7.1 | 7.3 | |
MP120_2 | 86.3 | 83.6 | 85.1 | 92.3 | 57.2 | 56.7 | 56.6 | 57.2 | |
MP30_5 | 34.24 | 34.2 | 36.44 | 39.04 | 23.16 | 23.28 | 22.48 | 23.36 | |
MP90_5 | 23.96 | 21.76 | 22.92 | 25.44 | 12.4 | 12.4 | 11.76 | 13 | |
MP120_5 | 104.04 | 104.44 | 106.56 | 112.64 | 67.72 | 68.32 | 67.56 | 67.8 | |
MP30_10 | 131.78 | 126.4 | 134.3 | 145.34 | 85.1 | 85.22 | 83.48 | 87.62 | |
MP90_10 | 104.14 | 106.72 | 108.96 | 114.3 | 61.34 | 60.4 | 61.12 | 62.1 | |
MP120_10 | 252.43 | 254.44 | 256.73 | 262.54 | 164.38 | 166.78 | 166.84 | 171.96 | |
MP30_20 | 333.61 | 340.69 | 338.15 | 352.6 | 205.06 | 208.3 | 203.74 | 213.16 | |
MP90_20 | 65.24 | 65.04 | 66.76 | 72.84 | 44.16 | 43.95 | 44.06 | 44.49 | |
MP120_20 | 71.28 | 70.49 | 71.48 | 77.56 | 47.48 | 48.28 | 47.24 | 47.52 | |
Average | 102.65 | 102.52 | 104.36 | 110.17 | 65.73 | 66.14 | 65.47 | 67.46 |
Problem subsets | Serial | parallel | |||||||
minTT | minGAP | maxRS | minRS | minTT | minGAP | maxRS | minRS | ||
MP30_2 | 14.8 | 13.7 | 14.8 | 16.1 | 13.9 | 13.3 | 13.7 | 14 | |
MP90_2 | 10 | 8.8 | 10.1 | 11.3 | 6.9 | 6.8 | 7.1 | 7.3 | |
MP120_2 | 86.3 | 83.6 | 85.1 | 92.3 | 57.2 | 56.7 | 56.6 | 57.2 | |
MP30_5 | 34.24 | 34.2 | 36.44 | 39.04 | 23.16 | 23.28 | 22.48 | 23.36 | |
MP90_5 | 23.96 | 21.76 | 22.92 | 25.44 | 12.4 | 12.4 | 11.76 | 13 | |
MP120_5 | 104.04 | 104.44 | 106.56 | 112.64 | 67.72 | 68.32 | 67.56 | 67.8 | |
MP30_10 | 131.78 | 126.4 | 134.3 | 145.34 | 85.1 | 85.22 | 83.48 | 87.62 | |
MP90_10 | 104.14 | 106.72 | 108.96 | 114.3 | 61.34 | 60.4 | 61.12 | 62.1 | |
MP120_10 | 252.43 | 254.44 | 256.73 | 262.54 | 164.38 | 166.78 | 166.84 | 171.96 | |
MP30_20 | 333.61 | 340.69 | 338.15 | 352.6 | 205.06 | 208.3 | 203.74 | 213.16 | |
MP90_20 | 65.24 | 65.04 | 66.76 | 72.84 | 44.16 | 43.95 | 44.06 | 44.49 | |
MP120_20 | 71.28 | 70.49 | 71.48 | 77.56 | 47.48 | 48.28 | 47.24 | 47.52 | |
Average | 102.65 | 102.52 | 104.36 | 110.17 | 65.73 | 66.14 | 65.47 | 67.46 |
Parameter | J | P | K | NC | RF | RS | ||
value | 5, 8, 10 or 14 | 2 or 3 | 4 | 1.5 | 0.25 | 0.2 |
Parameter | J | P | K | NC | RF | RS | ||
value | 5, 8, 10 or 14 | 2 or 3 | 4 | 1.5 | 0.25 | 0.2 |
instances | CPLEX | GA_maxRS (100 solutions) | (%) |
(%) |
(%) |
||||||
opt | worst | best | mean | ||||||||
J5_2 | 1 | 3 | 0.08 | 3 | 3 | 3 | 0.11 | 0 | 0 | 0 | |
2 | 1.5 | 0.03 | 1.5 | 1.5 | 1.5 | 0.14 | 0 | 0 | 0 | ||
3 | 2 | 0.05 | 2 | 2 | 2 | 0.1 | 0 | 0 | 0 | ||
4 | 5 | 0.08 | 5 | 5 | 5 | 0.15 | 0 | 0 | 0 | ||
5 | 2 | 0.05 | 2 | 2 | 2 | 0.13 | 0 | 0 | 0 | ||
J8_2 | 1 | 0.5 | 0.06 | 0.5 | 0.5 | 0.5 | 0.11 | 0 | 0 | 0 | |
2 | 1 | 0.09 | 1 | 1 | 1 | 0.17 | 0 | 0 | 0 | ||
3 | 2.5 | 0.08 | 2.5 | 2.5 | 2.5 | 0.2 | 0 | 0 | 0 | ||
4 | 5 | 0.3 | 5 | 5 | 5 | 0.24 | 0 | 0 | 0 | ||
5 | 3 | 0.2 | 3 | 3 | 3 | 0.31 | 0 | 0 | 0 | ||
J10_2 | 1 | 2.5 | 2.11 | 2.5 | 2.5 | 2.5 | 0.94 | 0 | 0 | 0 | |
2 | 9 | 3.72 | 9.5 | 9 | 9.1 | 0.87 | 6 | 0 | 1 | ||
3 | 10.5 | 2.23 | 12 | 10.5 | 11 | 1.06 | 14 | 0 | 5 | ||
4 | 7.5 | 3.2 | 7.5 | 7.5 | 7.5 | 0.56 | 0 | 0 | 0 | ||
5 | 7 | 4.83 | 7 | 7 | 7 | 1.42 | 0 | 0 | 0 | ||
J14_2 | 1 | 2 | 0.94 | 2.5 | 2 | 2.2 | 0.89 | 25 | 0 | 10 | |
2 | 6 | 25.23 | 6 | 6 | 6 | 0.99 | 0 | 0 | 0 | ||
3 | 4.5 | 1.91 | 5.5 | 4.5 | 4.7 | 1.18 | 22 | 0 | 4 | ||
4 | 7.5 | 30.42 | 7.5 | 7.5 | 7.5 | 1.5 | 0 | 0 | 0 | ||
5 | 4 | 15.2 | 6 | 4 | 5.5 | 1.45 | 50 | 0 | 38 | ||
J5_3 | 1 | 4.33 | 0.23 | 4.33 | 4.33 | 4.33 | 0.44 | 0 | 0 | 0 | |
2 | 2.67 | 0.63 | 3.67 | 3.33 | 3.53 | 0.82 | 37 | 25 | 32 | ||
3 | 4 | 0.86 | 5.33 | 4 | 4.67 | 0.61 | 33 | 0 | 17 | ||
4 | 3.33 | 0.19 | 4.33 | 3.33 | 3.94 | 0.45 | 30 | 0 | 18 | ||
5 | 3.33 | 0.7 | 3.33 | 3.33 | 3.33 | 0.63 | 0 | 0 | 0 | ||
J8_3 | 1 | 2 | 0.5 | 2 | 2 | 2 | 0.75 | 0 | 0 | 0 | |
2 | 7.67 | 15.69 | 8.67 | 7.67 | 7.94 | 1.18 | 13 | 0 | 4 | ||
3 | 2 | 0.22 | 2 | 2 | 2 | 0.58 | 0 | 0 | 0 | ||
4 | 6 | 152.2 | 8.33 | 6 | 6.47 | 1.85 | 39 | 0 | 8 | ||
5 | 1.33 | 0.41 | 1.33 | 1.33 | 1.33 | 0.66 | 0 | 0 | 0 | ||
J10_3 | 1 | 8.67 | 157.94 | 9.33 | 8.76 | 9.01 | 1.86 | 8 | 1 | 4 | |
2 | 10.67 | 249.08 | 11 | 10.67 | 10.79 | 1.67 | 3 | 0 | 1 | ||
3 | 4.33 | 320.17 | 5.67 | 4.33 | 4.79 | 1.27 | 31 | 0 | 11 | ||
4 | 8 | 824.63 | 8 | 8 | 8 | 1.28 | 0 | 0 | 0 | ||
5 | 6 | 1832.06 | 6 | 6 | 6 | 1.06 | 0 | 0 | 0 | ||
J14_3 | 1 | 6.33 | 131.98 | 6.33 | 6.33 | 6.33 | 2.14 | 0 | 0 | 0 | |
2 | 3.33 | 411.58 | 5 | 3.33 | 3.79 | 2.93 | 50 | 0 | 14 | ||
3 | 5.67 | 3600.44 | 6.67 | 5.67 | 5.79 | 3.03 | 18 | 0 | 2 | ||
4 | 11 | 3600.13 | 13.67 | 11 | 12.1 | 7.33 | 24 | 0 | 10 | ||
5 | 5 | 450.97 | 7 | 5 | 5.4 | 3.01 | 40 | 0 | 8 |
instances | CPLEX | GA_maxRS (100 solutions) | (%) |
(%) |
(%) |
||||||
opt | worst | best | mean | ||||||||
J5_2 | 1 | 3 | 0.08 | 3 | 3 | 3 | 0.11 | 0 | 0 | 0 | |
2 | 1.5 | 0.03 | 1.5 | 1.5 | 1.5 | 0.14 | 0 | 0 | 0 | ||
3 | 2 | 0.05 | 2 | 2 | 2 | 0.1 | 0 | 0 | 0 | ||
4 | 5 | 0.08 | 5 | 5 | 5 | 0.15 | 0 | 0 | 0 | ||
5 | 2 | 0.05 | 2 | 2 | 2 | 0.13 | 0 | 0 | 0 | ||
J8_2 | 1 | 0.5 | 0.06 | 0.5 | 0.5 | 0.5 | 0.11 | 0 | 0 | 0 | |
2 | 1 | 0.09 | 1 | 1 | 1 | 0.17 | 0 | 0 | 0 | ||
3 | 2.5 | 0.08 | 2.5 | 2.5 | 2.5 | 0.2 | 0 | 0 | 0 | ||
4 | 5 | 0.3 | 5 | 5 | 5 | 0.24 | 0 | 0 | 0 | ||
5 | 3 | 0.2 | 3 | 3 | 3 | 0.31 | 0 | 0 | 0 | ||
J10_2 | 1 | 2.5 | 2.11 | 2.5 | 2.5 | 2.5 | 0.94 | 0 | 0 | 0 | |
2 | 9 | 3.72 | 9.5 | 9 | 9.1 | 0.87 | 6 | 0 | 1 | ||
3 | 10.5 | 2.23 | 12 | 10.5 | 11 | 1.06 | 14 | 0 | 5 | ||
4 | 7.5 | 3.2 | 7.5 | 7.5 | 7.5 | 0.56 | 0 | 0 | 0 | ||
5 | 7 | 4.83 | 7 | 7 | 7 | 1.42 | 0 | 0 | 0 | ||
J14_2 | 1 | 2 | 0.94 | 2.5 | 2 | 2.2 | 0.89 | 25 | 0 | 10 | |
2 | 6 | 25.23 | 6 | 6 | 6 | 0.99 | 0 | 0 | 0 | ||
3 | 4.5 | 1.91 | 5.5 | 4.5 | 4.7 | 1.18 | 22 | 0 | 4 | ||
4 | 7.5 | 30.42 | 7.5 | 7.5 | 7.5 | 1.5 | 0 | 0 | 0 | ||
5 | 4 | 15.2 | 6 | 4 | 5.5 | 1.45 | 50 | 0 | 38 | ||
J5_3 | 1 | 4.33 | 0.23 | 4.33 | 4.33 | 4.33 | 0.44 | 0 | 0 | 0 | |
2 | 2.67 | 0.63 | 3.67 | 3.33 | 3.53 | 0.82 | 37 | 25 | 32 | ||
3 | 4 | 0.86 | 5.33 | 4 | 4.67 | 0.61 | 33 | 0 | 17 | ||
4 | 3.33 | 0.19 | 4.33 | 3.33 | 3.94 | 0.45 | 30 | 0 | 18 | ||
5 | 3.33 | 0.7 | 3.33 | 3.33 | 3.33 | 0.63 | 0 | 0 | 0 | ||
J8_3 | 1 | 2 | 0.5 | 2 | 2 | 2 | 0.75 | 0 | 0 | 0 | |
2 | 7.67 | 15.69 | 8.67 | 7.67 | 7.94 | 1.18 | 13 | 0 | 4 | ||
3 | 2 | 0.22 | 2 | 2 | 2 | 0.58 | 0 | 0 | 0 | ||
4 | 6 | 152.2 | 8.33 | 6 | 6.47 | 1.85 | 39 | 0 | 8 | ||
5 | 1.33 | 0.41 | 1.33 | 1.33 | 1.33 | 0.66 | 0 | 0 | 0 | ||
J10_3 | 1 | 8.67 | 157.94 | 9.33 | 8.76 | 9.01 | 1.86 | 8 | 1 | 4 | |
2 | 10.67 | 249.08 | 11 | 10.67 | 10.79 | 1.67 | 3 | 0 | 1 | ||
3 | 4.33 | 320.17 | 5.67 | 4.33 | 4.79 | 1.27 | 31 | 0 | 11 | ||
4 | 8 | 824.63 | 8 | 8 | 8 | 1.28 | 0 | 0 | 0 | ||
5 | 6 | 1832.06 | 6 | 6 | 6 | 1.06 | 0 | 0 | 0 | ||
J14_3 | 1 | 6.33 | 131.98 | 6.33 | 6.33 | 6.33 | 2.14 | 0 | 0 | 0 | |
2 | 3.33 | 411.58 | 5 | 3.33 | 3.79 | 2.93 | 50 | 0 | 14 | ||
3 | 5.67 | 3600.44 | 6.67 | 5.67 | 5.79 | 3.03 | 18 | 0 | 2 | ||
4 | 11 | 3600.13 | 13.67 | 11 | 12.1 | 7.33 | 24 | 0 | 10 | ||
5 | 5 | 450.97 | 7 | 5 | 5.4 | 3.01 | 40 | 0 | 8 |
Problem subsets | GA_maxRS | DMAS/RIA | (%) |
|||||
with TT | without TT | (%) |
with TT | without TT | (%) |
|||
MP30_2 | 13 | 10.9 | 19 | 23.3 | 18 | 29 | -39 | |
MP90_2 | 6.9 | 6.7 | 3 | 17.1 | 11.8 | 45 | -43 | |
MP120_2 | 56.1 | 55.6 | 1 | 89.6 | 80.3 | 12 | -31 | |
MP30_5 | 22.2 | 18.08 | 23 | 35.28 | 21.64 | 63 | -16 | |
MP90_5 | 11.68 | 9.36 | 25 | 22 | 13.32 | 65 | -30 | |
MP120_5 | 66.84 | 65.48 | 2 | 86.12 | 77.68 | 11 | -16 | |
MP30_10 | 81.58 | 78.16 | 4 | 92.68 | 83 | 12 | -6 | |
MP90_10 | 59.34 | 50.36 | 18 | 62.66 | 61.52 | 2 | -18 | |
MP120_10 | 164.28 | 140.3 | 17 | 162.6 | 144.1 | 13 | -3 | |
MP30_20 | 199.63 | 189.6 | 5 | 206.9 | 193 | 7 | -2 | |
MP90_20 | 43.38 | 34.92 | 24 | 42.88 | 43.13 | -1 | -19 | |
MP120_20 | 46.42 | 39.71 | 17 | 48.09 | 42.11 | 14 | -6 | |
Average | 64.28 | 58.26 | 10 | 74.1 | 65.8 | 13 | -11 |
Problem subsets | GA_maxRS | DMAS/RIA | (%) |
|||||
with TT | without TT | (%) |
with TT | without TT | (%) |
|||
MP30_2 | 13 | 10.9 | 19 | 23.3 | 18 | 29 | -39 | |
MP90_2 | 6.9 | 6.7 | 3 | 17.1 | 11.8 | 45 | -43 | |
MP120_2 | 56.1 | 55.6 | 1 | 89.6 | 80.3 | 12 | -31 | |
MP30_5 | 22.2 | 18.08 | 23 | 35.28 | 21.64 | 63 | -16 | |
MP90_5 | 11.68 | 9.36 | 25 | 22 | 13.32 | 65 | -30 | |
MP120_5 | 66.84 | 65.48 | 2 | 86.12 | 77.68 | 11 | -16 | |
MP30_10 | 81.58 | 78.16 | 4 | 92.68 | 83 | 12 | -6 | |
MP90_10 | 59.34 | 50.36 | 18 | 62.66 | 61.52 | 2 | -18 | |
MP120_10 | 164.28 | 140.3 | 17 | 162.6 | 144.1 | 13 | -3 | |
MP30_20 | 199.63 | 189.6 | 5 | 206.9 | 193 | 7 | -2 | |
MP90_20 | 43.38 | 34.92 | 24 | 42.88 | 43.13 | -1 | -19 | |
MP120_20 | 46.42 | 39.71 | 17 | 48.09 | 42.11 | 14 | -6 | |
Average | 64.28 | 58.26 | 10 | 74.1 | 65.8 | 13 | -11 |
[1] |
Reza Lotfi, Zahra Yadegari, Seyed Hossein Hosseini, Amir Hossein Khameneh, Erfan Babaee Tirkolaee, Gerhard-Wilhelm Weber. A robust time-cost-quality-energy-environment trade-off with resource-constrained in project management: A case study for a bridge construction project. Journal of Industrial & Management Optimization, 2020 doi: 10.3934/jimo.2020158 |
[2] |
Mohammed Abdulrazaq Kahya, Suhaib Abduljabbar Altamir, Zakariya Yahya Algamal. Improving whale optimization algorithm for feature selection with a time-varying transfer function. Numerical Algebra, Control & Optimization, 2021, 11 (1) : 87-98. doi: 10.3934/naco.2020017 |
[3] |
Guo Zhou, Yongquan Zhou, Ruxin Zhao. Hybrid social spider optimization algorithm with differential mutation operator for the job-shop scheduling problem. Journal of Industrial & Management Optimization, 2021, 17 (2) : 533-548. doi: 10.3934/jimo.2019122 |
[4] |
Min Ji, Xinna Ye, Fangyao Qian, T.C.E. Cheng, Yiwei Jiang. Parallel-machine scheduling in shared manufacturing. Journal of Industrial & Management Optimization, 2020 doi: 10.3934/jimo.2020174 |
[5] |
Yunfeng Geng, Xiaoying Wang, Frithjof Lutscher. Coexistence of competing consumers on a single resource in a hybrid model. Discrete & Continuous Dynamical Systems - B, 2021, 26 (1) : 269-297. doi: 10.3934/dcdsb.2020140 |
[6] |
Onur Şimşek, O. Erhun Kundakcioglu. Cost of fairness in agent scheduling for contact centers. Journal of Industrial & Management Optimization, 2020 doi: 10.3934/jimo.2021001 |
[7] |
Yuanshi Wang. Asymmetric diffusion in a two-patch mutualism system characterizing exchange of resource for resource. Discrete & Continuous Dynamical Systems - B, 2021, 26 (2) : 963-985. doi: 10.3934/dcdsb.2020149 |
[8] |
Tahir Aliyev Azeroğlu, Bülent Nafi Örnek, Timur Düzenli. Some results on the behaviour of transfer functions at the right half plane. Evolution Equations & Control Theory, 2020 doi: 10.3934/eect.2020106 |
[9] |
Lan Luo, Zhe Zhang, Yong Yin. Simulated annealing and genetic algorithm based method for a bi-level seru loading problem with worker assignment in seru production systems. Journal of Industrial & Management Optimization, 2021, 17 (2) : 779-803. doi: 10.3934/jimo.2019134 |
[10] |
Jie Shen, Nan Zheng. Efficient and accurate sav schemes for the generalized Zakharov systems. Discrete & Continuous Dynamical Systems - B, 2021, 26 (1) : 645-666. doi: 10.3934/dcdsb.2020262 |
[11] |
Fabio Camilli, Giulia Cavagnari, Raul De Maio, Benedetto Piccoli. Superposition principle and schemes for measure differential equations. Kinetic & Related Models, 2021, 14 (1) : 89-113. doi: 10.3934/krm.2020050 |
[12] |
Wolfgang Riedl, Robert Baier, Matthias Gerdts. Optimization-based subdivision algorithm for reachable sets. Journal of Computational Dynamics, 2021, 8 (1) : 99-130. doi: 10.3934/jcd.2021005 |
[13] |
Lin Jiang, Song Wang. Robust multi-period and multi-objective portfolio selection. Journal of Industrial & Management Optimization, 2021, 17 (2) : 695-709. doi: 10.3934/jimo.2019130 |
[14] |
Bilel Elbetch, Tounsia Benzekri, Daniel Massart, Tewfik Sari. The multi-patch logistic equation. Discrete & Continuous Dynamical Systems - B, 2021 doi: 10.3934/dcdsb.2021025 |
[15] |
Ivan Bailera, Joaquim Borges, Josep Rifà. On Hadamard full propelinear codes with associated group $ C_{2t}\times C_2 $. Advances in Mathematics of Communications, 2021, 15 (1) : 35-54. doi: 10.3934/amc.2020041 |
[16] |
Liang Huang, Jiao Chen. The boundedness of multi-linear and multi-parameter pseudo-differential operators. Communications on Pure & Applied Analysis, , () : -. doi: 10.3934/cpaa.2020291 |
[17] |
Yueh-Cheng Kuo, Huan-Chang Cheng, Jhih-You Syu, Shih-Feng Shieh. On the nearest stable $ 2\times 2 $ matrix, dedicated to Prof. Sze-Bi Hsu in appreciation of his inspiring ideas. Discrete & Continuous Dynamical Systems - B, 2020 doi: 10.3934/dcdsb.2020358 |
[18] |
Cheng Peng, Zhaohui Tang, Weihua Gui, Qing Chen, Jing He. A bidirectional weighted boundary distance algorithm for time series similarity computation based on optimized sliding window size. Journal of Industrial & Management Optimization, 2021, 17 (1) : 205-220. doi: 10.3934/jimo.2019107 |
[19] |
Editorial Office. Retraction: Honggang Yu, An efficient face recognition algorithm using the improved convolutional neural network. Discrete & Continuous Dynamical Systems - S, 2019, 12 (4&5) : 901-901. doi: 10.3934/dcdss.2019060 |
[20] |
Editorial Office. Retraction: Xiaohong Zhu, Zili Yang and Tabharit Zoubir, Research on the matching algorithm for heterologous image after deformation in the same scene. Discrete & Continuous Dynamical Systems - S, 2019, 12 (4&5) : 1281-1281. doi: 10.3934/dcdss.2019088 |
2019 Impact Factor: 1.366
Tools
Article outline
Figures and Tables
[Back to Top]